Challenge

Move a live data center — with no data loss.

The client ran a business-critical virtualized infrastructure in a legacy data center: aging hardware, limited scalability, and real operational risk around redundancy and disaster recovery.

The objective was to migrate the full production environment to a modernized platform with minimal downtime, no data loss, and complete business continuity.

Solution

A staged, rollback-ready migration.

Designed and executed an enterprise-grade migration strategy, run in stages to keep risk low:

  • Infrastructure assessment and dependency mapping
  • VM replication and synchronization
  • Incremental data transfer
  • Network reconfiguration planning
  • Rollback and disaster recovery procedures
  • Final cutover orchestration

A phased synchronization approach let the bulk of data transfer and VM preparation happen before the maintenance window — shrinking the actual cutover.

Results

A near-zero-disruption cutover.

13m 53s
Total downtime
99.98%
Service continuity during migration
0
Reported data corruption
  • Zero critical business-process interruption
  • Completed within the planned maintenance window
  • Successful post-migration validation of all services
  • Improved scalability and redundancy
  • Enhanced disaster recovery readiness
  • Reduced infrastructure risk
  • Improved performance and maintainability
  • Standardized virtualization environment

Technical specifications

Scale, stack and safeguards.

Infrastructure scale

  • 143 virtual machines
  • 20 TB replicated data
  • Multi-tier application environment
  • Production workloads
  • Hybrid Windows / Linux infrastructure
  • Active Directory integrated services
  • High-availability architecture

Virtualization / cloud stack

  • Proxmox VE
  • NAS storage
  • ZFS replication
  • Live migration orchestration
  • HA clustering
  • VLAN segmentation

Networking

  • Site-to-site VPN
  • Layer 2 migration strategy
  • Firewall rule migration
  • DNS transition planning
  • IP renumbering procedures
  • Reverse proxy migration
  • Load balancer failover

Reliability / continuity

  • Rollback-ready migration plan
  • Pre-migration validation
  • Snapshot-based recovery points
  • Replication integrity verification
  • Service dependency mapping
  • Disaster recovery procedures
  • Multi-stage testing environment
AuthorDmytro DoianovClientConfidential / NDADateMay, 2019Project TypeDatacenter MigrationIndustryLogisticsEnvironmentEnterprise InfrastructureResultNear-Zero DisruptionPartnerSIM-NetworksShare